Civil Engineers Guide

Primary Knowledge for Civil Engineers

1) First class brick weight should be not less than 3.85 kg 

2) Tensile strength of the first-class brick should not be less than 3000 lbs/per inch square

3) The normal building height should be 315 centi meter.

4) The normal height of the riser should be 15 centi meter.

5) One hook length should be not less than 9D.

6) First class brick should be observed the water 1/5 or 1/6 of the brick weight.

7) Window height should be 120 centi meters

 8) DBC thickness should be not less than 2.5 centi meters

9) Lintel thickness should be 15 centi meters

10) Normal and local sand FM limit should be 0.5 to 0.8

11) Cantiliver anchorage length for main steel is 69D.

12) Bend length (L) for column is minimum 300mm.

13) Chair, minimum diameter of bar is 12mm.

14) Minimum diameter of dowel bar is 12mm.

15) Lapping length should not be used for bar greater than 36mm.

16) Minimum numbers of bars for the square columns are 4 nos and for the circular column is 6 nos.

17) Longitudinal reinforcement should not be less than 0.8% and more than 6% for the gross cross-section.

18) The main bar in the slab shall not be less than 8 mm (HYSD) or 10mm (plain bar) and the distribution no less than 8mm and not more than 1/8 of slab thickness.

19) All reinforcement free from mill scales, loose rust, and courts of paints or oil and any other substances.

20) Dead Load means Self weight of Structure

21) DPC means Damp Proof Course. The DPC thickness should not be less than 2.5cm

22) If there is more than 5% moisture content in the sand,  that should not be used for concrete mix

23) The curing Period of RCC is 28days.

24) The transverse reinforcement provided in columns are called Ties

25) The transverse reinforcement provided in Beams is called as Stirrups

26) We use Stirrups in Beams and Ties in Column are provided to handle the shear force and to keep longitudinal bars in position. 

27)  M20 grade of concrete is used in the construction of slab.

28) Hook length should not be less than 9D. (Where D is Diamater of Bar) 

29) The rise in stairs is in between 150mm to 200mm. 

30) Tread in staircase is in between 250mm to 300mm. 

31) The slope or pitch of the stair should be in between 25 degrees to 40 degrees

32) Unit weight of PCC is 24KN/m², RCC is 25 KN/m² ‘Steel is 7850 Kg/m²

33) Cement more than 3 months old cannot be used for construction

34) Standard Size of Brick is 19cm x 9cm x 4cm.

Must Remember the Concrete Mix ratio of Different grades of Concrete atleast till M20 grade of concrete
Concrete Grade Mix Ratio
M5 1:5:10
M7.5 1:4:8
M10 1:3:6
M15 1:2:4
M20 1:1.5:3
M25 1:1:2
M30, M35, M40, M45, M50, M55, M60, M65, M70 Design Mix

Know about the Slump value of Concrete for Different concrete works

Concrete Mixes Slump range in mm
Columns, Retaining walls 75-150mm
Beams & Slabs 50-100mm
CC Pavements 20-30mm
Decks of bridge 30-75mm
Vibrated Concrete 12-25mm
Huge Mass constructions 25-50mm

Important short forms & full forms of civil engineering words

RCC  Reinforced Cement Concrete

 AE  Assistant Engineer

B.M – Benchmark / Bending moment

APM  Assistant Project Manager  

BHK  Bedroom, Hall, Kitchen  

BOQ  Bill Of Quantities

BWK  Brick Work  

W.C – Water closet.

CC Cement concrete / Centre To Centre

C.I.Sheet – Corrugated Iron sheet. 

CE  Chief Engineer 

CPM  Critical path method.

 Diameter  

D.L – Dead load

DPC  Damp proof course.  

DPR – Daily Progress Report

FL  Floor Level  

FOC  Factor Of Safety

GL  Ground Level  

JE  Junior Engineer

Kg  Kilogram 

L.L – Live load.

MFL  Maximum Flood Level

 Newton

OPC  Ordinary Portland Cement 

PCC  Plain Cement Concrete

PERT  Programme Evaluation and Review Technique.

PL  Plinth level.

QC  Quality control  

RCC  Reinforced Cement Concrete

RMC  Ready Mixed Concrete 

TDS  Total Dissolved Solids

W.C – Water closet.

WO  Work Order

Important Data for Civil Engineers

1) Slope of Staircase

The slope of staircase varies from 25° to 40° as per the Indian standard code 456-2000

2) Volume of Cement Bag

Weight of 1 cement bag is 50 kg so the volume of 1 cement bag is 0.0347 m³ or 1.23 CFT

3) Expiry Date of Cement Bags

Expiry date is 3 month after the bag is packed.

4) Why is Foundation Provided?

Foundation is provided in order to safely distribute the load of structure in the soil

5) Types of Foundations

Shallow foundation
Deep foundation

6) Calculation of weight of Steel bar

7) Minimum grade of concrete used for RCC

M20

8) Shuttering Removing Time

Side of wall column and Outer side of beam shuttering is removed after the 24 hrs to 48 hrs of concrete. Beam soffits shuttering is removed after 7 days. Slab shuttering is removed after 3 days. Remove the props of the slab after 21 days of span greater than 6m and after 14 days of span less than 6m.

9) What are the Concrete Tests?

Compressive strength test, Slump Test, Water absorption test, Water permeability test

10) What is the Unit Weight of Steel?

78.5 KN/m³ is the unit weight of steel.

11) Unit Weight of Concrete

The unit weight of concrete of RCC is 25 KN/m³ and PCC is 24 KN/m³

12) Compressive Strength of Bricks

First class Brick – 105 kg/cm²
Second class Brick – 70 kg/cm²
Fire Brick – 125 kg/cm²

13) The Setting Time of Cement

Initial setting time is 30 Minutes And the final setting time of cement is 90 minutes.

14) Curing Methods of Concrete

Spraying, Wet covering of Surface, ponding, Curing chemicals, Steam curing, Sprinkling

15) Function of Stirrups in Beams?

Stirrups are used in beams to resist shear force

16) Need of Pile Foundation

Pile foundation is acquired when the soil bearing capacity is less than 24 KN/m³

17) Standard Height

Height of each floor is 3 M

18) Grouting

It is a process in which a mixture of cement and sand proportion of 1:3 is shooted on the ground surface with the help of gun pressure of 2 to 3 kg/cm²

Following are basics of civil engineering points to remember for civil engineers to make the construction work easier while maintaining a quality of construction

  • Lapping in reinforcement is not allowed for the bars having diameters more than 36 mm.
  • Steel Char maximum spacing is 1.00 m (or) 1 No per 1m2.
  • In steel dowels, a rod minimum of 12 mm diameter should be used.
  • Steel Chairs minimum of 12 mm diameter bars to be used.
  • Longitudinal reinforcement should not less than 0.8% and more than 6% of gross C/S.
  • The minimum bars used for a square column are 4 No’s and 6 No’s for the circular column.
  • Main bars used in the slabs shall not be less than 8 mm (HYSD) or 10 mm (Plain bars) and the distributors not less than 8 mm and not more than 1/8 of slab thickness.
  • The minimum thickness of the slab should be 125 mm.
  • The freefall of concrete is allowed a maximum of 1.50m in height.
  • Lap splices shall not be used for bars larger than 36 mm.
  • Water absorption of bricks limited not more than 15 %.
  • PH value of the water used should not be less than 6.
  • The minimum Compressive strength of Bricks is 3.5 N / mm2.
  • The binding wire required in steel reinforcement is 8 kg per Metric tonne.
  • For soil filling work as per IS code, 3 samples should be taken for core cutting test for every 100m2.

Density of Construction Materials

  • Bricks – 1600 – 1920 kg/m3
  • Concrete block – 1920 kg/ m3
  • Reinforce Concrete – 2310 – 2700 kg/ m3

Curing Time for Concrete Members for Various Type of Cement

Curing of Concrete

  • Super Sulphate cement: 7 days
  • Ordinary Portland cement OPC: 10 days
  • Minerals & Admixture added cement: 14 days

De-Shuttering Period of Different RCC Members

  • The period for columns, walls, vertical formworks – 16-24 hrs.
  • Period for Soffit formwork to slabs – 3 days (props to be refixed after removal)
  • The period for Soffit to beams props – 7 days (props to be refixed after removal)
  • Beams spanning up to 4.5m – 7 days
  • Beams spanning over 4.5m – 14 days
  • Arches spanning up to 6m – 14 days
  • Arches spanning over 6m – 21 days